Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Just Posted

Former Comox hospital turning into Vancouver Island’s first ‘dementia village’

Island Health inks deal to transform St. Joseph’s Hospital into groundbreaking $52.6 million facility

Vancouver Island hasn’t seen a new homegrown case of COVID-19 in two weeks

Island’s low and steady transmission rate chalked up to several factors

Three people facing mischief charges after protests at Premier John Horgan’s home

Special prosecutor was appointed to avoid real or perceived undue influence

Eight people arrested on Pandora Avenue after enforcement order issued

Those living in homeless camps were given until May 20 to move indoors

Vancouver Island churches embrace technology to cope with pandemic

Technology helping faith communities connect

Ferry sailings scheduled once again at Nanaimo’s Departure Bay terminal

BC Ferries announces that resumption of service June 3 includes four daily round trips

‘A bottomless well of love for people and communities’

Parksville Qualicum Beach News editor JR Rardon dies at age 61

Dump truck in Nanaimo snags power lines, snaps hydro pole, crashes

No injuries in incident Monday morning on Old Victoria Road

Kelowna man charged with harming a hamster

The 20-year-old Kelowna man faces several animal cruelty charges

No one injured in suspicious Victoria boat fire, say investigators

Victoria police and fire personnel called to blaze on waters near Selkirk Trestle May 22

Victoria dealer sells Batmobile replica at Arizona auction

Tim Quocksister sells Batmobile replica for $165,000 US at auction in Scottsdale, Ariz.

Snowbirds jets will not be leaving Kamloops, just yet

The Snowbirds have been in Kamloops since May 17 when a plane crashed killing Capt. Jennifer Casey

COVID-19 checkpoints ‘up to them,’ Bonnie Henry says of remote B.C. villages

Support local tourism economy, but only if you’re invited in

Most Read