The new mooring dolphin at Pier B will accommodate larger cruise ships. (Don Descoteau/News Staff)

Replacement steel for sunk cargo on the way

Steel needed for Victoria cruise ship dock coming after first attempt sank

For the second time in a year, the Greater Victoria Harbour Authority (GVHA) is awaiting the arrival of a huge shipment of steel to complete the mooring dolphin expansion at Pier B of The Breakwater District (formerly Ogden Point).

In January, on day 29 of a 30-day journey, a $3-4 million shipment of steel coming from China sank after the cargo ship hit a storm.

READ MORE: Piece for pier extension at Ogden Point Cruise Terminal lost at sea

This made the GVHA have to get creative with its space so it could still accommodate the largest ship to ever moor at the pier, the Royal Caribbean’s Ovation of the Seas.

“We made it work,” said Ian Robertson, CEO of the GVHA. “We planned to berth the Ovation of the Seas alongside the Breakwater at Pier A, but had to put on some restrictions for higher winds because that location isn’t optimal.”

In the meantime, an order was placed for a second rendition of the required steel, which includes a 200-foot long, 10-foot wide and 400,000 lb steel pipe, as well as several steel piles.

Luckily, due to the fact that the steel had been organized by a subcontractor, the GVHA was not financially responsible for the loss of the steel. Additionally, because the GVHA have an agreement with a committed price for the construction, the $6.8 million budget has not increased.

ALSO READ: Ogden Point officially rebranded as The Breakwater District

“It was an unfortunate and unpreventable accident,” Robertson said. “But we weren’t in jeopardy of any financial risk due to the loss.”

The new shipment arrived by freighter at the Fraser Surrey Docks, and in a few days will be transferred to a barge. It is set to arrive at The Breakwater District in 10-14 days, after which construction will begin immediately.

Robertson said if all goes well, construction will be done in about three months, well ahead of the date of the first cruise ship arrival on April 3.

nicole.crescenzi@vicnews.com

Like us on Facebook Send a Tweet to @NicoleCrescenzi
and follow us on Instagram

Ogden Point

Just Posted

COVID-19: Island crisis line calls rise as restrictions ease

Organization reminds people of their range of services

Duncan’s Queen Margaret’s School pioneers thermal imaging in school reopening

Duncan school is first in B.C. to use new tech post-COVID-19

Saanich man dies from injuries after serious crash on Six Mile Road

Police continue to investigate cause of fatal crash

Grieving together, but apart: How funeral homes are handling the pandemic

‘Hugs are so important and right now hugs can’t happen’

George Floyd asphyxiated by sustained pressure: family autopsy

Death sparked a wave of protests across the U.S. and abroad

COVID-19: B.C. commercial landlords can’t evict if they decline rent assistance

Emergency order ‘incentive’ for federal program, Carole James says

Trans Mountain starts B.C. leg of pipeline twinning project

Mostly finished in Alberta, Burnaby terminal expanding

House burns in Nanaimo neighbourhood, three people displaced

Dog unaccounted for after house fire Sunday evening

RCMP remind drivers of school zone safety as classes resume

As kids return to school, the police will be watching

BC Transit rate change, embarking rules shift into action June 1

Campbell River transit system getting a new day pass

Number of students returning is a wild card as B.C. schools reopen Monday

A common model will see other teachers work four days a week in class then the fifth remotely,

Classes in Comox Valley to look a little different in June

School district senior staff has been busy prepping for re-opening

Most Read