First Nation calls for release of Site C report in open letter to premier

The letter says BC Hydro has withheld its two latest progress reports from regulators

A First Nations leader is calling on the British Columbia government to release several reports on the Site C dam, claiming details of escalating costs and safety concerns have been “shrouded in secrecy.”

In an open letter to Premier John Horgan, Chief Roland Willson of the West Moberly First Nations says work on the hydroelectric dam in northeastern B.C. should be suspended immediately until cabinet makes a decision on the project.

“You can reject the madness of ploughing ahead with this unnecessary, unsafe, and unlawful project. You can choose instead to immediately suspend the project,” the letter says.

The letter says BC Hydro has withheld its two latest progress reports from regulators and the premier has refused to release a report prepared by special adviser Peter Milburn.

Although BC Hydro initially said the reports were commissioned by the government and referred comment to the province, it later clarified that the progress reports are its responsibility.

The Crown corporation said in a statement it is undergoing a re-baselining process for the project and will file its next progress report with the B.C. Utilities Commission after that is complete.

The Energy Ministry said in a statement it is reviewing Milburn’s advice and “will share the findings as soon as possible.”

In addition, government is awaiting a report from two independent international experts who are reviewing the measures proposed to address geotechnical challenges at Site C, the ministry said.

The ministry did not respond directly to questions about whether it would pause the project or respond to allegations that the project infringes on the First Nation’s treaty rights.

Willson said in an interview if the reports aren’t made public voluntarily, the First Nation will seek their release through court action.

The First Nation has already prepared a notice of application and served the parties with a motion but is awaiting scheduling availability before filing the document with the court, said Tim Thielmann, a lawyer for the First Nation.

If the documents reveal significant safety risks, costs or scheduling implications, the First Nation may apply for a second injunction against the project. When the B.C. Supreme Court denied an injunction in October 2018, it said a new injunction could be granted if there was “unforeseen and compelling change in circumstances,” he said.

“If we find out that there is a serious safety risk or financial implication that justifies another injunction, then the court has left the door open for West Moberly to bring a new injunction,” Thielmann said.

Soon after taking power, Horgan announced in December 2017 that the government would support completion of Site C, but said it is a project the NDP would never have started.

BC Hydro reported to the B.C. Utilities Commission in July that geotechnical problems found in late 2019 had created a “project risk,” requiring stability measures to be taken on the right bank of the dam.

The B.C. government appointed Milburn, a former deputy finance minister, in July to review the project. Energy Minister Bruce Ralston said this month he wouldn’t discuss its findings until they are reviewed by the premier and cabinet.

Willson said in an interview that the hydroelectric dam is an unnecessary infringement of the First Nation’s treaty rights and he doesn’t believe the community’s concerns have been taken seriously.

“It’s a shame we’re at this stage. We should have never gotten this far down the road. We should have sat at the table like adults,” Willson said.

The Peace River, where the dam will sit, runs through the heart of the First Nation’s territory, Willson said.

“We’re sitting here watching our valley get ripped apart,” he said. “Our spiritual areas are getting destroyed, our burial sites along the river are getting destroyed.”

Treaty members still live near the site and work should be halted if there are real safety concerns, he said.

Given the government’s stated commitment to the United Nations Declaration on the Rights of Indigenous Peoples, Willson said he’s disappointed the government is allowing the project to forge ahead.

The First Nation has already asked the government to share the reports but decided to pen the open letter after hearing no response, he said.

“It’s ridiculous. We’re in an age of reconciliation. We wanted to sit down with them and have a conversation with them about how we can meet the energy needs of B.C. without flooding the valley,” Willson said.

“We want to give them a chance to do the right thing.”

BC Hydro said in a statement that since 2007, it has undertaken extensive and meaningful consultation and engagement with First Nations on Site C and reached benefits agreements with the majority of Treaty 8 First Nations that have been affected by the project.

“We’re committed to working with Indigenous communities and building relationships that respect their interests,” it said.

The project is designed to the highest recommendations of the Canadian Dam Association, it said.

“Safety has been — and will always be — our key priority.”

The Canadian Press

Like us on Facebook and follow us on Twitter.

Want to support local journalism? Make a donation here.

Site C

Just Posted

Comox Valley RCMP had access to 20 Street blocked off between Cousins and Choquette avenues as they conducted a raid of a house on the block. Photo by Terry Farrell
Comox Valley RCMP raid Courtenay problem house, several arrests made

Neighbours have reached out to media on several occasions with complaints about the property

Darcy Rhodes (left) says his grandfather’s bonsai trees are his ‘babies.’ (Courtesy of Tamara Bond)
Construction takes place on Bamfield Main in early February 2021. (PHOTO COURTESY CTV NEWS)
Ongoing Bamfield roadwork unrelated to planned $30M fix

Construction by Mosaic unrelated to $30M upgrade ordered in wake of fatal bus crash

Protestors against old growth logging gather in front of the courthouse in Victoria on Thursday morning. (Don Denton/Black Press Media)
Fairy Creek protesters gather at Victoria courthouse

Logging company seeks injunction to remove blockades near its Port Renfrew operation

One person is dead after a camper van caught fire Thursday morning in Victoria's Beacon Hill Park. (Nina Grossman/News Staff)
UPDATED: One person dead after vehicle fire in Beacon Hill Park

Investigation into Victoria death in early stages

B.C. Health Minister Adrian Dix and provincial health officer Dr. Bonnie Henry head for the B.C. legislature press theatre to give a daily update on the COVID-19 pandemic, April 6, 2020. (B.C. government)
B.C. nears 300,000 COVID-19 vaccinations, essential workers next

564 new cases, four deaths, no new outbreaks Thursday

Municipal Affairs Minister Josie Osborne speaks in the B.C. legislature, March 4, 2021. (Hansard TV)
B.C. Liberals, NDP sing in harmony on local election reforms

Bill regulates paid canvassers, allows people in condo buildings

The intersection of Melrose Street and Third Avenue. (ELENA RARDON / ALBERNI VALLEY NEWS)
Suspect in custody after two pedestrians struck in Port Alberni hit and run

RCMP asking for video footage, credit witnesses for quick arrest

(National Emergency Management Agency)
No tsunami risk to B.C. from powerful New Zealand earthquake: officials

An 8.1 magnitude earthquake shook the north of New Zealand Thursday morning

(AP Photo/Richard Vogel, File)
Pandemic stress, isolation key factors as to why Canadians turned to cannabis, alcohol

Study found that isolation played key role in Canadians’ substance use

Crews disassemble the iconic red and white KFC bucket from a sign on Goldstream Avenue. (Photo courtesy of Mark Schoor)
Iconic KFC bucket removed from Goldstream Avenue

Popular fast-food chain closes Langford location

Grand Forks’ Gary Smith stands in front of his Church of the Flying Spaghetti Monster float. Photo: Submitted
Grand Forks’ Flying Spaghetti Monster leader still boiling over driver’s licence photo

Gary Smith, head of the Church of the Flying Spaghetti Monster of B.C., said he has since spoken to lawyers

(Pxhere)
B.C. research reveals how pandemic has changed attitudes towards sex, health services

CDC survey shows that 35 per cent of people were worried about being judged

Clockwise from top left: Malahat First Nation Chief George Harry and councillors Steve Henry and Cindy Harry address community members in a video posted to YouTube on Wednesday, March 3, 2021. (Screenshot)
Malahat Nation confirms first two cases of COVID-19

Community has been under stay-at-home order since Jan. 7

Most Read