Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Just Posted

Thousands of cigarette butts collected and recycled from downtown Victoria

Canisters placed throughout the downtown core have made an impact on local litter

CPR month promotes hands-on approach to life-saving

PulsePoint Respond App alerts people if there is a victim of a cardiac arrest within 400 metres

Column: It’s a bit late to demand total plant consumption

Veganism/vegetarianism don’t take into account global impacts or historical realities, says columnist

One dead after fiery crash in Duncan

A driver has died after a fiery motor vehicle collision in Duncan… Continue reading

Disney Plus gives Canadians a streaming platform that nearly matches U.S. version

The Walt Disney Company’s new subscription platform unveiled a comprehensive offering of nearly 500 films

Bill Murray dons iconic Hudson’s Bay scarf to watch Canucks game in Vancouver

Murray is in Vancouver to film The Now, a mini-series directed by Peter Farrelly

Canadian allergists’ group wants Benadryl behind the counter due to side effects

Some doctors say the medication is over-used because of its easy availability

B.C. government grappling with multiple labour disputes by public-sector unions

Public-sector unions may have expectations of a labour-friendly NDP government

‘We love you, Alex!’: Trebek gets choked up by ‘Jeopardy!’ contestant’s answer

The emotional moment came in Monday’s episode when Trebek read Dhruv Gaur’s final answer

Police say simple changes can take the target off your home

Two reports of prowlers in one night in Esquimalt

Students calling on the province to step in and end strike

SD63 students to gather at Minister of Education’s office while strike continues into third week

Cures for those times when your travels ail you

Experts share solutions for jet lag, motion sickness, food poisoning, and other travel maladies

Paella for one: Barcelona dazzles when you’re travelling solo

Solo means no judgement when you stop for gelato or churros and chocolate twice a day

Most Read