Site C dam benefits undersold, consultant says

Union group hires former Columbia Power CEO to study project

Scrapping the Site C dam project would cost $4 billion and B.C. Hydro would then have to start developing riskier alternatives, says a new analysis of the project.

The Allied Hydro Council of B.C., a group of heavy construction unions, hired a former CEO of Columbia Power Corp., Lorne Sivertson, to analyze the recent review ordered by Premier John Horgan of the third dam on the Peace River. Sivertson said the B.C. Utilities Commission (BCUC) made “serious errors,” including under-valuing Site C’s reliable power output and B.C.’s future power needs.

At a news conference in Vancouver Wednesday to release the report, Sivertson was joined by energy lawyer Jim Quail to argue that Site C should go ahead, despite the B.C. Liberal government’s rush to get it going without independent analysis of its needs and risks.

“While we can all agree that the B.C. Liberal government was incredibly reckless in not putting Site C to a full review by the BCUC years before construction started and letting all interested parties submit evidence for consideration, the province now has to decide how best to proceed with the funding already invested,” Quail said.

Sivertson had a list of criticisms of the BCUC findings, conducted this fall with a Nov. 1 deadline imposed by the incoming NDP government. They include:

• If B.C.’s energy demand grows by just one per cent per year from 2017 to 2036, and federal and provincial targets to reduce greenhouse gas emissions are to be met, “the equivalent of three Site C dams will be needed”

• The BCUC described the project’s demand forecast as too optimistic, but “if the demand for electric vehicles continues to grow as rapidly as recent statistics show, even B.C. Hydro’s growth forecast will be low.”

• The BCUC’s suggestion to use power now sold to the U.S. under the Columbia River Treaty runs the risk that the U.S. will cancel the treaty

• B.C. Hydro’s growth projections are not dependent on development of a liquefied natural gas industry.

Allied Hydro Council of B.C. business agent Wayne Peppard also touted the benefits of returning to project labour agreements, essentially making Site C a closed shop for traditional building trade union workers, to keep the project on schedule.

BC HydroBC legislatureSite C

Just Posted

Nikita, a four-year-old German Shepherd that was attacked by a buck in a backyard in Esquimalt Sunday is lucky the injury wasn't more severe. (Photo contributed by Suzette Goldsworthy)
Esquimalt dog owner issues alert after deer injures German shepherd

Nikita needed stitches after an early morning encounter

Windy conditions in Nanaimo’s Lost Lake area. (News Bulletin file photo)
Wind warning issued for the east coast of Vancouver Island

Environment Canada says people ‘should be on the lookout’ for adverse weather conditions

Volunteers gather at Third Avenue and Mar Street on Friday, Nov. 20, 2020 to walk the streets of Uptown Port Alberni searching for people sleeping in alleys to hand out food and Naloxone kits. (SUBMITTED PHOTO)
Port Alberni tent city evicted again

Campers took over gazebo at Roger Creek Park

A deer pokes through the gardens at Beacon Hill Park. The Royal BC Museum. (Nina Grossman/News Staff)
Esquimalt mayor repeats call for regional approach to urban deer management

Province waiting on Oak Bay results, Desjardins says cost of duplicating process ‘considerable’

Nanaimo Fire Rescue Chief Karen Fry will become the next fire chief of Vancouver Fire and Rescue Services in the new year. (News Bulletin file photo)
Nanaimo’s fire chief hired to become Vancouver’s fire chief

Karen Fry calls the move a ‘once-in-a-lifetime’ opportunity

People wearing face masks to help curb the spread of COVID-19 cross a street in downtown Vancouver, on Sunday, November 22, 2020. The use of masks is mandatory in indoor public and retail spaces in the province. THE CANADIAN PRESS/Darryl Dyck
B.C. reports 17 COVID deaths, 1,933 new cases as hospitalizations surge over the weekend

There are 277 people in hospital, of whom 59 are in ICU or critical care

B.C. Liberal interim leader Shirley Bond speaks to reporters from Prince George via Zoom conference, Nov. 24, 2020. MLAs are being sworn in for the legislature session this week, many of them also by video. (B.C. legislature)
B.C. Liberal leadership contest will wait for election post-mortem

Interim leader set to face NDP on payments for COVID-19

Construction has started on a new apartment complex at 1025 Ryan Rd. in Courtenay. Scott Stanfield photo
Courtenay apartment to contain 118 units

Construction underway on complex featuring rent-capped units

Aerial shot of a section of the Hartland landfill in Saanich. First Nations company KENES Transportation will be trucking biosolids from the residuals treatment facility at Hartland to the Lafarge Canada cement plant in Richmond (YouTube/Capital Regional District)
CRD, First Nations sign contract to haul biosolids to Mainland cement plant

Deal ‘hits the triple bottom line of positive social, environmental and financial impact,’ says CRD

Those looking for shelter at Warmland House may soon find that option limited as Warmland cuts capacity during the COVID-19 pandemic. (File photo)
Warmland House in Duncan cutting back on shelter beds due to COVID

Decision a safety precaution during pandemic

Product Care offers more than <a href="http://link.mediaoutreach.meltwater.com/ls/click?upn=pDYyTceU0YgTDdsd92GohdQJsmSiPFEkcB4MdMM0Qkoqb1aJA-2By5aWklKJXV6QRdyTteNjr2FccUOVLUe4t5Zw-3D-3D1ds-_KVyBcpjXADXifSWVpM8nQcAzSm9-2B6fEFnjVrTsOcu31irDHDxi5k0QTOIWCqMXUxaNbrf0yRzXSSpROCkfx3NkUtbr65Dkcw1J0by-2F-2BDdDiJGbcfhtjHWYSs66NwakeCCLYkj20e9ICIZsLcedqNZKBhsN0sGgBsInpdzsddYikUZkmQvFdxLJhakpgAA6aAJ5ScUoWR6vO9sM819vRB-2F6x7dsdfIaWa4ZgHxR4G7hauxgSJCsNI2bP5J62EFfM0aiDqRPwUPUjt7i5-2FMqpdJxrEBewnLky-2B3lE0JAmi5UsJBkJejuLOjsndZz4b7dNgbvt6KyewKuF0sxU2rpYgkAO9YAKc9STuFJd28Qn7jE0-2FqlB8HKOvpW150NHS-2BOMBcK5rkZ8YAuPqJy11k-2BgndiKB-2FWl2icAfbWtRGJPb8fM-3D" target="_blank">150 free drop-off locations</a> in B.C. (Pixabay.com)
Recycling broken or burnt string lights can reduce holiday landfill waste

In 2019, Product Care Recycling diverted more than 11.6 million light bulbs from landfills

Most Read